First check is needed after the very first unpacking. It consists from box content check after the first box opening and essential security checks to get information about overall box state. Note that all boxes were on the transport for more than one year an it's potentially dangerous to use them without serious control.
Note: it's recommended to apply essential security checks on annualy base
Watch online
Download full HD video
Following procedures must be performed after BB3 is unpacked and before it goes configurated. If not, there is a risk of fire or explosion in case of charging/discharging pending. This action allows:
Watch online
Download full HD video
Note: all temperature sensors reads values and then they are averaged for a few seconds by mainboard processor, Sometimes, you have to wait for a few seconds to get exact values especially after boot or changes in a configuration.
If battery voltage of new open box is 13.2V at least, this procedure is not necessary but still recommended. You have o start with battery cover opening.
Watch online
Download full HD video
Watch online
Download full HD video
Watch online
Download full HD video
After the measurement, compare each cell voltages. The difference between cells should not be more than 0.05V If is it higher, consult this with support head engineer or in the support group on WhatsApp before you are going to plug this BB to the grid, solar panel or use in field.
Important note:
Ensure that all wires (especially car plug wires) are properly connected. Then rise lid a bit, inser car plug into its space, bend the lid a bit and insert it side by side.
Watch online
Download full HD video
To charge BB3 from AC wall plug, you will need a "PC power cable" It's a standard AC cable used for PC stations. If you need to charge BB3 from wall plug and don't have one, ask your Head Engineer to get one. AC power can be used either for changing battery and for normal operations. But the most common expected operations is from solar charger. If you are about to use AC plug as the main power for operation, charge battery first (don't transmit unless battery are charged) To get battery fully charged using AC wall plug takes 6hrs est. if battery is fully discharged. As AC power is presented, AC indicator green LED light ON even when protection switch is OFF and BB3 is not charging from this port.
Note: you may use both charging systems (solar and AC) simultaneously. Then, charging time is faster.
Watch online
Download full HD video
After connecting to AC wall plug, You should see that battery voltage increases slowly. Maximum charging voltage is 14,5V. Standby voltage of fully charged battery is around 13.4 ~ 13.6V according to ambient temperature.
Note: If battery voltage drops bellow 10V, BMS disconnects cells from the system so BB3 will not work unless get charged from any source.